Reconfigure the chart above into a critical path diagram for project scheduling similar to the diagram shown in this module’s lecture, homework help

Description

In a 1-page Word document, consider the following activities and their durations. The original project schedule, using early activity starts, is shown below.

Activity Task Predecessors Duration Activity Cost
A Sign Contract None 5 days $5,000
B Design Survey A 3 days $1,500
C Identify Audience A 7 days $1,000
D Run Survey B, C 30 days $6,000
E Analyze Results D 5 days $3,000
F Create Presentation E 5 days $1,000
G Present to Client E, F 2 days $3,000
  • Reconfigure the chart above into a critical path diagram for project scheduling similar to the diagram shown in this module’s lecture.
  • What is the duration of the project?
  • How much slack is currently available in the non-critical path?
  • How long are the project and feeder buffers?

Needs help with similar assignment?

We are available 24x7 to deliver the best services and assignment ready within 6-12hours? Order a custom-written, plagiarism-free paper

Get Answer Over WhatsApp Order Paper Now

Do you have an upcoming essay or assignment due?

All of our assignments are originally produced, unique, and free of plagiarism.

If yes Order Paper Now